BSS
  27 Mar 2024, 15:55

Govt extends timeframe for 3 power plants

DHAKA, March 27, 2024 (BSS) - The Cabinet Committee on Government Purchase 
(CCGP) today extended the timeframe for procuring electricity from three gas-
based power plants by five more years operated by Summit Power Limited.

The approval came from its seventh meeting in this year held today at the 
Cabinet Division Conference Room of Bangladesh Secretariat here with Finance 
Minister Abul Hassan Mahmood Ali in the chair.

Briefing reporters after the meeting, Cabinet Division Secretary 
(coordination and reforms) Md Mahmudul Hossain Khan said that the day's 
meeting approved a total of three proposals.

He said following a proposal from the Power Division, the CCGP meeting 
extended the timeframe for these three gas-based power plants by another five 
years from the date of expiry on November 22, 2023.

Mahmudul said the tariff for these three power plants would be lower this 
time as it would be Taka 6.04 per unit for which around Taka 6.81 crore would 
be saved in this fresh five-year tenure. These power plants would be operated 
under "No Electricity, No Payment" basis while there will be only operational 
charge, he added.

The minister informed that the CCGP meeting also approved a proposal from the 
Energy and Mineral Resources Division for signing the fifth supplementary 
agreement with EPC contractor China Petroleum Pipeline Engineering Co Ltd 
(CPPEC) for procuring tugboat with sufficient capacity, pilotage and availing 
ancillary services for successfully completing the testing and commissioning 
work under the project for "Installation of single point mooring (SPM) with 
double pipeline" being implemented by the Eastern Refinery Limited (ERL).

The meeting also approved a cost variation proposal from the Ministry of 
Railways.
 