Rajshahi ZP auditorium renovation at final stage

593

RAJSHAHI, June 13, 2018 (BSS)-Falling behind the schedule for at least six
years, the work on modernization of the 800-seat Rajshahi Zila Parishad (ZP)
auditorium is now at the final stage.

Rajshahi City Corporation (RCC) had started the necessary renovation of the
auditorium on November 4, 2011 with an estimated cost of Taka 4.69 crore. The
project was scheduled to be accomplished in June 2012.

The then ZP administration gave the responsibility of implementing the
development work to RCC due to its shortage of technological knowhow and
manpower.

Ashraful Haque, chief engineer of RCC, said work on infrastructure
development, seating installation, modern electricity supply and sound system
were completed with the allocated money. But, all the scheduled works could
not be completed within the stipulated time due to fund constraint, he
informed.

Recently, the RCC got Taka 1.20 crore from Fazley Hossain Badsha, MP, for
completing the unfinished work on commissioning air-condition and sound
system in the auditorium.

“We are very much hopeful about completion of the work within a shortest
possible time”, said Engineer Haque.

Lawmaker Badsha told local journalists that 16 projects now are being
implemented in the city at a cost of around Taka seven crore at his own
initiative. Implementation of the unfinished work on the ZP auditorium is one
of those.

Muhammad Ali Sarker, chairman of ZP, said Rajshahi people will get services
of the auditorium upon successful implementation of its modernization works.

Besides, the auditorium will reopen up doors of ZP’s income together with
contributing a lot towards flourishing cultural practice of the metropolis,
he added.